Liesfeld undertook the demolition of existing hardscape in downtown Richmond and the excavation and removal of nearly 140,000 cubic yards of earthen material to create the basement footprint of the new Philip Morris Research and Technology Park. Upwards of ninety dump trucks were employed daily to haul the excavated material from the site in order to facilitate our client’s sixty day start to finish schedule. We completed the required excavation four days ahead of schedule.