Vulcan Materials – Royal Stone Overburden

Specs

Project: Vulcan Materials – Royal Stone Overburden
Location: Rockville, Virginia
Category:
Client: Vulcan Materials
Contract Value: $500,000
Completion Date: 2014
Job Duration: 2 Months
Engineer:

About this project

In 2014, Liesfeld moved 225,000 cubic yards of overburden material at Vulcan Material’s Royal Stone Quarry in Rockville, Virginia. Liesfeld also installed several thousand feet of V Ditches that had mixtures of rip rap and slope stabilization matting. The project utilized Liesfeld’s mining support operations in moving over 10,000 cubic yards per day.

 

 

 

 

 

 

 